Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

–10z – 28z a. 38z b. –38z c. 18 d. 18z
how does the concept of competition relate to the arms race between the united states and the soviet union during the cold war?
hat is the 68th term of sequence -8.6,-7.2,-5.8,-4.4,
The following sequence represents an arithmetic sequence. 1, 2, 3, 4, 1, 2, 3, 4, . . . true false
Chemistry help asap please :(
a company pays $379.50 for its employees to attend a luncheon. if the cost is $8.25 per person, how many employees does the company have?
Early human populations were controlled by all of these factors except? is it predation, disease, pollution, food availability.
What term refers to a system in which one branch of government is prevented from seizing too much power?
Completely factor the polynomial. 4x^2 20x 25
what is the product of the binomial (x+4)(x+3)