15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

A woman can bike 5 miles in one stretch. Her long-term goal is to bike 20 miles in one stretch. What is an appropriate short-term goal for her? to bike 3 miles
(3×7)+5=26 write a situation for this equation and draw a picture that goes with it​
Whats black and white abd has lots of problems
Grain and what other product were shipped to the manufacturing centers of the East by railroad​
Given the formula for an arithmetic sequence f(9) = f(8) + 5 written using a recursive formula, write the sequence using an arithmetic formula. f(9) = f(1) + 5
73. The study of life
What are good strategies for overcoming writer’s block procrastination?
a small class has 10 students, 4 of whom are girls and 6 of whom are boys. the teacher is going to choose two of the students at random. what probability that
How have humans changed the atmosphere of the planet in the past 200 years
How do scientists know that Utahraptor ever lived