A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

How do you work out the problem 84 divided by4
State two ways in which a single-celled organism, such as amoeba, and a human body are alike?
when we look at a leaf, we see the colors of light that are reflected off its surface. how does the relatively low flow of oxygen in green light?
Why were the 1920's considered the best and worst of times?
How did the depression affect women and children?
What is a series of events that cells go through as they grow and divide
What sorts of signals does the brain use to communicate sensations, thoughts and actions?
How did the depression affect women and children?
What is a series of events that cells go through as they grow and divide
Morgan found a stone arrowhead. He measured it three times. He measured it as 2 inches to the nearest inch, to the nearest 1/2 inch, and to the nearest 1/4 inch