a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

a carbonated drink is absorbed how compared to alcohol
The price of an item yesterday was 110. Today the price fell to 33 find the percentage decrease
How are events in a story that are told in chronological order presented to the reader?
Which characteristics are not necessarily true of all living things
Fran drew a triangle with no congruent sides and one right angle which term accurately describes a triangle mark all that apply it is not a test but it just say
-6x^3y+2xy^2-3xy, para x = 1/6 e y = 1
Which exocrine structure is involved in the digestion of fat?
Rhubarb is used in making pies, tarts, and sauces. If a cook makes 2 pints of rhubarb sauce, will there be at least 5 cups of sauce made?
The majority of Portugal's colonies in Africa were located? a. Southern Africa b. Eastern Africa c. Northern Africa d. North Western Africa
Calculate the molarity of a solution containing 5.6 mol of sodium hydroxide dissolved in 2.1 L of water